Mep Work Progress Report Sample ((top)) -
Sample 2: Quantitative Tabular Format (Excel/Dashboard Style)
Delay in delivery of main DBs; Mitigation: Supplier expedited to deliver by [Date]. 2. Detailed Progress Tracking Activity Description Progress (%) Mech AHU Ducting Installation Mech Chilled Water Piping Elec Cable Tray Installation Elec Wiring/Conduit Plumb Drainage Risers All Levels Fire Sprinkler Installation 3. Manpower Summary Engineers/Supervisors: 5 Technicians/Electricians: 25 Plumbers/Pipefitters: 20 Helpers: 30 Total Daily Average: 80 4. Material Deliveries & Status
Continue main cable pulling from the main switchgear room up to the Level 4 electrical closet. Conduct air leakage testing on Level 4 HVAC duct networks. 4. Key Performance Indicators (KPIs) to Track mep work progress report sample
Main power cabling pulled from the main switchgear room to the electrical risers up to Level 4.
Issue reports at strict, predictable intervals (e.g., every Friday afternoon or the first day of every month). Consistent reporting helps teams spot negative progress trends before they jeopardize the final deadline. predictable intervals (e.g.
: Supports accurate billing and provides a record for future warranty claims. Core Components of an MEP Progress Report
Number of inspections submitted, approved, or rejected. mep work progress report sample
Tracking MEP progress requires a different approach than tracking structural or architectural work.
A comprehensive report generally includes the following sections:
Delayed delivery of AHUs due to customs clearance bottlenecks. Impact: Delays mechanical connection work on Floor 4.
Installed 85% of high-density polyethylene (HDPE) soil and waste vertical stacks.